Actions
Items that need to be completed within this phase
- Brainstorming and Strategic Planning
- Executive Director approval to initiate
- Request an ITPMO Project Manager
Additional Actions for Platinum and Gold Projects
Required steps if your project's band level is platinum or gold
- Pre-Initiation Brief to your Organizational Leadership Team
- Organizational Approval to Initiate with CIO approval for ITS Departments
Move to phase 2
Once you've completed all the steps in Phase 1: Pre-Initiation, you will move on to Phase 2: Initiation