Project and Subproject Timeline
View Timeline Data
Data Centers and Servers
Phase Timelines:
Initiation
Wednesday, April 1, 2015 to Sunday, May 31, 2015
Planning
Monday, June 1, 2015 to Saturday, October 31, 2015
Implementation
Sunday, November 1, 2015 to Wednesday, August 1, 2018
Closeout
Thursday, August 2, 2018
Implementation - Stage 1 - Low Hanging Fruit
Wednesday, July 1, 2015 to Thursday, June 30, 2016
Implementation - Stage 2 - Enhancements and mid-level consolidations
Friday, July 1, 2016 to Friday, June 30, 2017
Implementation - Stage 3 - Consolidate Remaining Rooms
Saturday, July 1, 2017 to Saturday, June 30, 2018
Implementation - Stage 4 - Finalize Consolidation
Sunday, July 1, 2018 to Tuesday, July 31, 2018
Macro Audits
Phase Timelines:
Macro Audits
Friday, July 10, 2015 to Wednesday, October 7, 2015
Audit reviews
Thursday, October 8, 2015 to Wednesday, October 21, 2015
Bowen Science Building Decommission
Phase Timelines:
4-530 BSB
Friday, August 14, 2015
MRC Decommission
Phase Timelines:
114 MRC
Tuesday, June 2, 2015 to Friday, August 28, 2015
Chemistry Building Decommissions
Phase Timelines:
E127A-1 CB
Friday, April 17, 2015 to Wednesday, October 21, 2015
W174 CB
Friday, April 17, 2015 to Wednesday, October 21, 2015
W338 CB
Friday, April 17, 2015 to Wednesday, October 21, 2015
University Capitol Centre Decommissions
Phase Timelines:
2440 UCC
Monday, October 26, 2015 to Thursday, December 31, 2015
2627 UCC
Tuesday, January 26, 2016 to Thursday, March 30, 2017
Biology Building Decommission
Phase Timelines:
B38B BB
Wednesday, October 7, 2015 to Tuesday, December 8, 2015
Boyd Law Building Decommissions
Phase Timelines:
48 BLB
Wednesday, July 22, 2015 to Tuesday, January 5, 2016
48A BLB
Wednesday, July 22, 2015 to Tuesday, January 5, 2016
Seamans Center Decommission
Phase Timelines:
1309 SC
Thursday, October 15, 2015 to Thursday, December 31, 2015
Seashore Hall Decommission
Phase Timelines:
E212-B1 SSH
Saturday, February 6, 2016 to Monday, February 8, 2016
Engineering Research Facility Decommission
Phase Timelines:
235 ERF
Thursday, September 3, 2015 to Thursday, February 18, 2016
Wendell Johnson Speech and Hearing Center Decommission
Phase Timelines:
320 SHC
Monday, September 14, 2015 to Wednesday, April 6, 2016
Westlawn Decomissions
Phase Timelines:
2181A WL
Tuesday, July 28, 2015 to Wednesday, April 13, 2016
2181J-5 WL
Tuesday, July 28, 2015 to Wednesday, April 13, 2016
Philip D. Adler Journalism and Mass Communication Building Decommission
Phase Timelines:
30 AJB
Thursday, September 24, 2015 to Friday, May 6, 2016
Studio Arts Building Decommission
Phase Timelines:
1101B-1 SA
Thursday, February 18, 2016 to Friday, May 6, 2016
Van Allen Hall Decommission
Phase Timelines:
209 VAN
Thursday, March 31, 2016 to Monday, August 29, 2016
508 VAN
Wednesday, August 24, 2016 to Thursday, February 9, 2017
Continuing Education Facility
Phase Timelines:
211B CEF
Monday, May 9, 2016 to Monday, October 24, 2016
Clinton Street Building
Phase Timelines:
110A CLSD
Thursday, September 1, 2016 to Monday, February 27, 2017
Iowa Memorial Union
Phase Timelines:
132E IMU
Tuesday, June 14, 2016 to Sunday, May 7, 2017
Roy G. Karro Athletic Hall of Fame
Phase Timelines:
015-1 KHF
Wednesday, October 12, 2016 to Thursday, May 4, 2017
Pappajohn Business Bldg
Phase Timelines:
C240J PBB
Monday, November 28, 2016 to Friday, July 7, 2017
Spence Laboratories of Psychology
Phase Timelines:
G14A-1 SLP
Monday, November 23, 2015 to Monday, August 7, 2017
Iowa Advanced Technology Laboratory
Phase Timelines:
285 IATL
Wednesday, June 1, 2016 to Tuesday, September 26, 2017